| 1 | 28/01/2026 | 2412001360 | Dayat | 🏗️ Project | Terminasi |
Pemasangan suport chaint hoist. Line 10 sudah selesai.
|
🖼️ 1 foto | |
| 2 | 27/01/2026 | P12-167 | - | 🔧 Maintenance | Penerangan |
Perapian kabel power lampu PJU area bengkel
|
🖼️ 1 foto | |
| 3 | 27/01/2026 | P12-167 | - | 🏗️ Project | Penerangan |
Lepas lampu HB LD Palletizer L8 smentara
|
🖼️ 1 foto | |
| 4 | 27/01/2026 | 2312001331 | Fedryk | 🏗️ Project | Penerangan |
Pulling cable.
|
Tidak ada | |
| 5 | 27/01/2026 | 2412001360 | Dayat | 🏗️ Project | Terminasi |
Terminasi SDP convenyor LINE 10 dr filling line 10 sudah selesai.
|
🖼️ 1 foto | |
| 6 | 26/01/2026 | P15-375 | Raharjo | 🏗️ Project | Penerangan |
Pekerjaan di gudang sewa beji
1.
-memasang panel slim 4 pcs di office rawmate
-memasang stop kontak 1 pcs di office rawmate
-Menambah pemasangan panel slim 2 pcs di lab QAS
-memasang stop kontak area musholla lantai 2
|
🖼️ 1 foto | |
| 7 | 26/01/2026 | P12-167 | - | 🏗️ Project | MPD / SDP |
Penarikan kabel power ;
SDP Filling 10 to SDP Conveyor 10 (Belum Selesai)
|
🖼️ 1 foto | |
| 8 | 26/01/2026 | 2412001360 | Dayat | 🔧 Maintenance | Terminasi |
Perbaikan tombol rollig dor rawmat sudah selesai
|
🖼️ 1 foto | |
| 9 | 26/01/2026 | 2412001360 | Dayat | 🔧 Maintenance | Fabrikasi Panel |
Perbaikan tombol rolling dor loading dok rawmat sudah selesai
|
🖼️ 1 foto | |
| 10 | 23/01/2026 | P12-167 | - | 🏗️ Project | Terminasi |
penarikan dan terminasi kabel Grounding ;
SDP Filling 10 to conveyor 10
SDP Filling 7 to Conveyor 10
Panel Grounding to Conveyor 10
Cleaning area SDP Filling 8-10
|
🖼️ 1 foto |